Enter Budget Cost Directly into Primavera P6
From Enterprise
> Resource Dictionary,
>Resource Id "BOQ"
>Resource Name "x"
>Resource Type "Material"
Go to ActivityDetail Tab
> ResourceTab
> Add Resource
> Select BOQ (Resource Id)
Now go to Status Tab
> Right Corner See Labour unit
> Change to Material Cost
> Budget Cost
> enter the Cost Directly.