G.I.Pipe Railing on Bridges

click for excel file
G.I.Pipe Railing on Bridges

 Material   S.NO.              1               1               2               3
 Dia of pipe in inches              2                  2               2
 Thickness of wall in mm              3      
 Rate per 100'              4       10,125       14,250       14,250
 Adustorum 1%              5           101           112           112
 Wastage 2%              6           203           224           224
 Specials 20%              7        5,063        2,850        7,125
 Surface Treatment outer surface with paint              8           450           500           500
 Total 4+5+6+7+8              9       15,941       17,936       22,211
 Contractor,s Profit 10%            10        1,594        1,425        2,043
 Total            11       17,535       19,361       24,254
       
 Labour   No of joints in line            12               5               5               5
 Progress            13               8               5               5
 Daily labour  chargeses            14        1,155        1,155        1,155
 Cost per joint            15           144           231           231
  Jointing material+threading, fixing in P.C.C 1:2:4
(P.joint)  
          16           200           250           250
 Total(15+16)*12            17        1,144        1,481        2,405
 Carriage            18           153           153           153
 Testing            19             50             50             50
 Total            20        1,348        1,684        2,608
       
 Add 10% Contractor's profit 17+18+19            21             -               -             261
 Total            22             -               -             261
       
 RATE   Composite for 100 (11+22)            23               8               5               5
 Labour for per foot20/100            24               -               -  
 Composite for per foot 21/100            25           190               0               0
 LABOUR     
 Plumber   1No            300
 Coolie              2           300
 Mason              1           150
 Painter              1           300
 Total           1,050
 Add10%Sundr              105
 Total           1,155